Onshore and offshore oil and gas well construction
Technical and technological solution for carrying out a multi-stage hydraulic fracturing in a well and a device for its implementation

UDC: 622.276.66
DOI: 10.33285/0130-3872-2021-12(348)-50-52

Authors:

KORABELNIKOV MIKHAIL IVANOVICH1,
BASTRIKOV SERGEY NIKOLAEVICH1,
AKSENOVA NATALIA ALEXANDROVNA1,
LIPATOV EVGENY YURIEVICH1

1 Tyumen Industrial University, Nizhnevartovsk, Russian Federation

Keywords: well; production; oil; multi-stage hydraulic fracturing of a formation; production casing string; pipe branch

Annotation:

The article provides a variant of solution to the problem of carrying out an expensive technological operation of a multi-stage hydraulic fracturing. The authors of the article, within the framework of the import substitution program, propose using a technology and a technical device for carrying out a multistage hydraulic fracturing. Equipping the production casing string by pipes with a weakened cross-section, equipped with a brittle bitumen bandage and a wear-resistant material casing, allows creating a large number of hydraulic fracturing intervals in one approach to the well using a tubing assembly with a selective packer.

Bibliography:

1. Proskurin V.A. Sovershenstvovanie tekhnologiy mnogostadiynogo gidrorazryva plasta v gorizontal'nykh skvazhinakh: dis. … kand. tekhn. nauk: 25.00.17. – Ufa, 2013. – 123 s.
2. Govzich A.N., Bilinchuk A.V., Fayzullin I.G. Opyt provedeniya mnogostadiynykh GRP v gorizontal'nykh skvazhinakh OAO "Gazpromneft'" // Neft. khoz-vo. – 2012. – № 12. – S. 59–61.
3. Pat. 2682391 Ros. Federatsiya, MPK E21B 43/26, F16K 17/14. Sposob provedeniya pointerval'nogo gidrorazryva plasta v skvazhine i ustroystvo dlya ego osushchestvleniya / M.I. Korabel'nikov, A.M. Korabel'nikov; patentoobladatel' Tyumenskiy industrial'nyy un-t. – № 2018100447; zayavl. 09.01.2018; opubl. 19.03.2019, Byul. № 8.