Analysis of the relationship between the pace of construction work and the cost of constructed objects
UDC: 621.643.07
DOI: 10.33285/1999-6934-2023-4(136)-52-56
Authors:
VASILIEV GENNADY G.1,
KAZANTSEVA DARYA A.1
1 National University of Oil and Gas "Gubkin University", Moscow, Russia
Keywords: linear object construction flows, optimal pace of construction works, estimated cost of construction works, methods of mathematical statistics, probability of works duration
Annotation:
The article considers the problem of selecting the optimal pace of construction works at their minimum estimated cost. Special attention is paid to the acceptability of mathematical statistics methods to improve the validity of calculations for determining the optimal duration of works and the scheme of construction. A method for calculating the probability of works completion within a certain period of time with an appropriate degree of reliability to approximate the reality of schedules and plans of construction organizations is presented.
Bibliography:
1. Sbornik ukrupnennykh pokazateley stoimosti stroitel'stva (UPSS) ob"ektov OAO "Gazprom". Ch. 1. – M.: Gazprom, 2013. – 82 s.
2. Vasil'ev G.G., Ivanets V.K., Kazantseva D.A. Printsipy modelirovaniya protsessa realizatsii proektov stroitel'stva ob"ektov truboprovodnogo transporta // Avtomatizatsiya i informatizatsiya TEK. – 2022. – № 1(582). – S. 37–43. – DOI: 33285/2782-604X-2022-1(582)-37-43
3. Laptev A.A. Sistema upravleniya proektami stroitel'stva magistral'nykh truboprovodov s primeneniem informatsionno-kommunikatsionnykh tekhnologiy: dis. … d-ra tekhn. nauk: 25.00.19. – M., 2003. – 283 s.
4. Konstantinova L.I. Teoriya veroyatnostey i matematicheskaya statistika: ucheb. posobie. – Tomsk: Izd-vo TPU, 2010. – 153 s.
5. Stankevich V.M. Sovremennye metody opredeleniya prodolzhitel'nosti vremeni, neobkhodimogo dlya provedeniya stroitel'nykh rabot, po faktu i normativam // E-Scio. – 2020. – № 3(42). – S. 320–324.