Oilfield engineering
Risk based inspection methodology: current challenges and solutions

UDC: 658.58
DOI: 10.33285/0207-2351-2023-1(649)-35-40

Authors:

BRIKOV ALEXANDER V.1,
ALEXANDROVICH SERGEY I.1

1 Arctic SPG 2, Novy Urengoy, Russia

Keywords: risk based inspection, risk factor, industrial safety, standardization, inspection, corrosion, remaining life

Annotation:

The paper outlines particular challenges of risk based inspection (RBI) approach application for equipment inspection in Russia fuel and energy industry. Solutions to improve efficacy of inspection in current situation are provided. Risk based inspection is applied in industry worldwide for more than 20 years. Methodology proved its safety and efficacy. Russian industry started application of RBI methodology just recently. However currently strong interest of industry is observed. Some companies actively use that methodology, others are just at the beginning of the way. Main factor preventing from RBI roll-out is absence of regulatory framework. Therefore, the first step for RBI program implementation shall be a development of legal regulatory requirements. In addition, methodological framework of RBI is essential. That requires a revision of existing national standard, which shall consider international standards provisions and specific aspects of local industry, current industrial safety system. RBI assessment shall be conducted by qualified and experienced personnel. That is required of development and setup of national education and certification system. RBI assessment is a complex task, which usually requires special software. In this regards development of local RBI software is one of the priorities especially in view of sanctions and localization. Addressing of these problems will allow to use all benefits of RBI methodology and improve efficacy and safety of operating facilities.

Bibliography:

1. Demenkova K.R., Chuykov D.A., Smetankina G.I. Primenenie risk-orientirovannogo podkhoda pri osushchestvlenii kontrol’no-nadzornoy deyatel’nosti, problemy i perspektivy razvitiya // Pozharnaya bezopasnost’: problemy i perspektivy. – 2019. – № 10. – S. 93–95.

2. Ivashina M.M., Natsypaeva E.A., Popova L.F. Risk-orientirovannyy podkhod kak napravlenie sovershenstvovaniya sistemy menedzhmenta kachestva promyshlennykh predpriyatiy // Ekonomicheskiy zhurnal. – 2018. – № 2(50). – S. 26–39.

3. American Society of Mechanical Engineers, Risk-Based Inspection – Development of Guidelines, Vol. 1, General Document, CRTD-Vol. 20-1, ASME Research Task Force on Risk-Based Inspection Guidelines, Washington, DC, 1991.

4. American Society of Mechanical Engineers, Risk-Based Inspection – Development of Guidelines, Vol. 2, Part 1, Light Water Reactor (LWR) Nuclear Power Plant Components, CRTD-Vol. 20-2, ASME Research Task Force on Risk-Based Inspection Guidelines, Washington, DC, 1992.

5. American Society of Mechanical Engineers, Risk-Based Inspection – Development of Guidelines, Vol. 2, Part 2, Light Water Reactor (LWR) Nuclear Power Plant Components, 1996.

6. American Society of Mechanical Engineers Research White Paper, Risk-Based Alternative Selection Process For Inservice Inspection of LWR Nuclear Power Plant Components, November 1995.

7. Phillips J.H. Development of the Risk-Based Inspection Techniques and Pilot Plant Activities, SE9800027. – URL: https://inis.iaea.org/collection/NCLCollectionStore/_Public/29/015/29015615.pdf (data obrashcheniya: 10.06.2022).

8. API PUBL 581. – 1st Ed. – 2000. – Risk-Based Inspection Base Resource Document.

9. API Recommended Practice 580. – 1st Ed. – May 2002. – Risk-Based Inspection.

10. EN 16991. – April 2018. – Risk-based inspection framework.

11. API 580 Recommended Practice. – 3rd Ed. – February 2016. – Risk-Based Inspection.

12. API 581 Recommended Practice. – 3rd Ed. – April 2016. – Risk Based Inspection Methodology.

13. ASME PCC-3-2017. Inspection Planning Using Risk-Based Methods.

14. DNV-RP G101. Risk Based Inspection Of Offshore Topsides Static Mechanical Equipment. – October 2010.

15. EEMUA Publication 159. – 5th Ed. – 2018. – Above ground flat bottomed storage tanks – a guide to inspection, maintenance and repair.

16. EPRI Topical Report TR-112657, Revision B-A. – December 1999. – Revised Risk-Informed In-service Inspection Evaluation.

17. Proposed Guideline for Reliability-Based Bridge Inspection Practices / G. Washer, M. Nasrollahi, C. Applebury [et al.] // NCHRP Report 782. Transportation Research Board of the National Academies, Washington, DC, 2014.

18. SPC/TECH/GEN/46. Version 4. Risk based inspection (RBI) – A risk based approach to planned plant inspection.

19. API 510. – 10th Ed. – May 2014. – Pressure Vessel Inspection Code: In-service Inspection, Rating, Repair, and Alteration.

20. API 570. – 4th Ed. – February 2016. – Piping Inspection Code: In-service Inspection, Rating, Repair, and Alteration of Piping Systems.

21. API 653. – 3rd Ed. – December 2001. – Tank Inspection, Repair, Alteration, and Reconstruction.

22. Braginskiy O.B. Neftegazovyy kompleks mira – M.: Izd-vo "Neft’ i gaz" RGU nefti i gaza im. I.M. Gubkina, 2006. – 640 s.

23. Singurov A.A., Deryabin P.G. Inspektsiya oborudovaniya s uchetom faktorov riska v kompanii "Sakhalin Enerdzhi" // Gazovaya prom-st’. – 2018. – № 12. – S. 114–121.

24. Kunin V.A., Uporova I.V. Risk-orientirovannyy podkhod kontrol’no-nadzornoy deyatel’nosti: mezhdunarodnyy opyt i osobennosti primeneniya v rossiyskikh usloviyakh // Ekonomika i upravlenie. – 2019. – № 2(160). – S. 59–68.

25. Sbornik pravil i rukovodyashchikh materialov po kotlonadzoru / sost. L.B. Sigalov. – Izd. 4, pererab. i dop. – M.: Nedra, 1977. – 576 s.

26. Prikaz № 521 ot 11 dekabrya 2020 g. "ob utverzhdenii federal’nykh norm i pravil v oblasti promyshlennoy bezopasnosti "Pravila bezopasnosti ob"ektov szhizhennogo prirodnogo gaza". – URL: http://publication.pravo.gov.ru/Document/View/0001202012210129 (data obrashcheniya: 10.06.2022).

27. GOST R 55234.4-2013. Prakticheskie aspekty menedzhmenta riska. Protsedury proverki i tekhnicheskogo obsluzhivaniya oborudovaniya na osnove riska. – URL: https://standartgost.ru/g/GOST_R_55234.3-2013 (data obrashcheniya 10.06.2022).

28. DS/CWA 15740. – 2008 Ed. – May 14 2008. – Risk-Based Inspection and Maintenance Procedures for European Industry (RIMAP).

29. Opyt vnedreniya sistemy upravleniya riskami i nadezhnost’yu oborudovaniya na osnove programmnogo kompleksa PCMS / E.I. Kopalidi, S.A. Lapkin, V.R. Rzhevkin, A.B. Samokhvalov // Khimicheskaya tekhnika. – 2016. – № 2. – S. 28–31.

30. Rzhevkin V.R., Samokhvalov A.B., Shemyakin V.V. PCMS – programmnoe obespechenie dlya upravleniya sostoyaniem oborudovaniya zavoda na osnove otsenki riskov // Tekhnologiya mashinostroeniya. – 2014. – № 2. – S. 49–53.